- • Nepal Electricity Authority (NEA) successfully restored power to six flood-affected municipalities in Nuwakot district (Kharanitar, Samundratar, Chaugada, Likhu, Panchakanya, and Bidur) following Bhotekoshi River flooding through deployment of alternative transmission infrastructure.
- • NEA implemented alternative power routing from Sindhupalchok, utilizing the Chapali–Devighat 66 kV and 11 kV transmission lines to bypass damaged primary infrastructure and restore service to affected communities.
- • Spokesperson Rajan Dhakal confirmed technical teams are actively charging alternative lines, indicating a phased restoration approach focused on re-establishing critical grid connectivity in flood-impacted zones.
- • The restoration effort demonstrates NEA's operational resilience and infrastructure redundancy capabilities in managing supply disruptions from natural disasters in Nepal's mountainous terrain.
Summary
According to NEA Spokesperson Rajan Dhakal, technical teams are actively charging the Chapali–Devighat 66 kV and 11 kV transmission lines to facilitate power delivery through these alternative routes. The restoration strategy leverages an alternative line originating from Sindhupalchok, which now serves as the primary routing mechanism for electricity supply to the flood-impacted municipalities in Nuwakot.
This restoration approach underscores NEA's capacity to maintain grid stability and service continuity during infrastructure disruptions caused by natural disasters. The deployment of alternative transmission lines represents standard utility response protocols for managing supply restoration in geographically challenging and flood-prone regions. The phased technical implementation, as evidenced by ongoing line charging activities, indicates a methodical approach to ensuring safe and sustained power delivery restoration across affected communities.