Microsoft’s Project Kilby aims for power delivery by 2028, Stifel says

Reported by Cryptobriefing
Jun 24, 2026· 3 min read
Save Post LinkedIn Email
Key Takeaways
  • • Chevron and Microsoft signed a 20-year power agreement for Project Kilby, a 2.67-gigawatt natural gas power plant in Reeves County, West Texas, with first power delivery expected in late 2028.
  • • Project Kilby will consume approximately 2.7 gigawatts of electricity—equivalent to powering roughly 2 million homes—dedicated entirely to Microsoft's data center operations without grid connection.
  • • Power generation will utilize gas turbines supplied by GE Vernova and Caterpillar, with excess capacity available for grid stabilization over time, according to Chevron's new energies president Jeff Gustavson.
  • • Microsoft plans to allocate $190 billion in capital expenditures this year (up 61% from 2025) to support massive data center buildout for artificial intelligence applications, with this partnership demonstrating willingness to leverage natural gas alongside renewable energy investments.
  • • Chevron expects to make a final investment decision on the project later in 2026, with full site build-out continuing into the 2030s, positioning the partnership as potentially one of the largest co-located power and data center developments in the U.S.
Summary
Chevron and Microsoft have entered into a landmark 20-year power supply agreement for Project Kilby, a dedicated natural gas power generation facility in Reeves County, West Texas. The facility is designed to deliver approximately 2.67 gigawatts of capacity—enough electricity to power roughly 2 million homes—exclusively to Microsoft's adjacent artificial intelligence data center. Initial power delivery is anticipated in late 2028, with full buildout continuing through the 2030s. Chevron has not yet commenced construction and expects to finalize its investment decision later in 2026.

The power generation infrastructure will rely on large-scale gas turbines provided by strategic partners GE Vernova and Caterpillar. A key operational feature is that the electricity will be dedicated to the data center and remain disconnected from the regional electrical grid, eliminating direct competition with local utility consumers. Jeff Gustavson, president of Chevron's new energies division, emphasized this advantage while noting that as the facility generates excess capacity, that power can be introduced to the grid to provide stabilization support. This model positions the project as a self-contained energy solution capable of contributing to grid resilience.

Microsoft's engagement in this natural gas partnership reflects its aggressive capital deployment strategy to support accelerating artificial intelligence infrastructure demands. The company has announced $190 billion in capital expenditures for 2026—a 61% increase compared to 2025—with a substantial portion directed toward data center expansion. Noelle Walsh, Microsoft's president of cloud operations and innovation, stated that the "rapid growth of AI requires energy infrastructure that can scale quickly and reliably." While Microsoft has traditionally emphasized renewable energy investments to offset carbon dioxide emissions, this partnership with Chevron demonstrates pragmatic acceptance of fossil fuel infrastructure to meet near-term scaling requirements at competitive costs.

Chevron's positioning as a primary energy supplier leverages its access to natural gas resources from the Permian Basin in West Texas and southeastern New Mexico, enabling rapid and cost-effective power delivery to data center operations. The arrangement underscores the emerging intersection of energy commodities and technology infrastructure investment, with major technology platforms increasingly requiring long-term, dedicated power supply agreements backed by traditional energy companies to sustain computational capacity growth.

Go deeper than the headline

Research every firm in this story, track the ones that matter and get the daily briefing — free for 7 days.

Start your free 7-day trial

Sources

1 outlet

AlphaMaven summarised this story from the reporting below. Each link opens the original article.

Cryptobriefing Microsoft’s Project Kilby aims for power delivery by 2028, Stifel says