  • • Demolition underway at 350 Park Avenue: The 1.8 million square-foot supertall office tower project in Midtown East Manhattan has begun physical demolition, with Vornado Realty Trust executive Glen Weiss publicly reaffirming the company's commitment at a Real Deal forum last week.
  • • Ken Griffin's participation remains uncertain: While Vornado and co-developer Rudin are actively proceeding, Griffin's Citadel has stated its commitment to the project is "under review" following public criticism from New York City officials, creating material deal risk.
  • • Significant financial commitment: Vornado is investing $300 million to $400 million for a 36% to 40% ownership stake in the development, with construction previously planned for April 2026.
  • • Major NYC office anchoring: The 62-64 story, 1,600-foot supertall will be anchored by Citadel and is expected to create 6,000 construction jobs and support the creation of 15,000+ permanent positions in the Manhattan office market.
  • • Exit optionality preserved: Vornado retains contractual rights to exit the partnership in mid-July (per SEC filings), providing downside protection if Griffin withdraws, though such a scenario could derail the entire project.
Summary
The 350 Park Avenue supertall development in Midtown East Manhattan has entered the active demolition phase, marking a critical juncture for one of New York City's most closely watched commercial real estate projects. Vornado executive vice-president Glen Weiss publicly affirmed the company's commitment at a recent Real Deal industry forum, stating "We've started demolition and we're ready to roll" and pushing back against media reports questioning the project's viability. The development partnership includes Vornado Realty Trust, the Rudin organization, and Ken Griffin's Citadel, with Vornado investing $300 million to $400 million for an ownership stake of 36% to 40%.

However, significant uncertainty surrounds Griffin's continued participation. Citadel has characterized its commitment as "under review" in response to public criticism from New York City officials, including remarks from Mayor Zohran Mamdani. This creates material risk to deal completion, as Vornado has disclosed in SEC filings that it retains contractual rights to exit the partnership in mid-July, likely triggered by a Griffin withdrawal. Industry executives acknowledge the political headwinds but remain focused on project execution. CBRE Global Brokerage chief Stephen Siegel noted that Griffin's previously announced plans to expand office space in Miami were unrelated to recent political pressure and predate the controversy.

The planned 62-64 story, 1,600-foot structure will deliver approximately 1.8 million square feet of office space anchored by Citadel and is projected to generate 6,000 construction jobs and support 15,000+ permanent positions. The New York City Council previously approved the project unanimously. The development represents a "once-in-a-generation" commercial real estate opportunity for Midtown Manhattan's office market recovery, though its execution now hinges on whether Griffin maintains his investment commitment alongside Vornado and Rudin.

Go deeper than the headline

Research every firm in this story, track the ones that matter and get the daily briefing — free for 7 days.

Start your free 7-day trial

Sources

1 outlet

AlphaMaven summarised this story from the reporting below. Each link opens the original article.

Nypost Ken Griffin’s Park Ave. project with Vornado set for major update this week - New York Post